Türkiye Electricity Transmission Inc. (TEİAŞ), T.C. In line with its Decision dated 16.03.2023 and numbered 11731 taken by the Energy Market Regulatory Board (EMRA), an announcement regarding capacity allocations has been published. Aforementioned…

In line with the Board Decision of EMRA, the regional capacities prepared by TEIAS are as follows:
1- PROJECTS OR FACILITIES WITH THE MAIN SOURCE OF WIND OR SUN AND CONVERSION TO MULTI-SOURCE ELECTRICITY FACILITIES, EXCEPT FOR PROJECTS OR FACILITIES WITHOUT AUXILIARY SUPPLY BY WIND OR SUN: FOR PROJECTS DEMANDED AND COVERED, FOR MWA 510

2- CAPACITIES FOR GENERATION FACILITY REQUESTS TO BE CONNECTED TO THE SYSTEM FROM THE TRANSMISSION LEVEL WITHIN THE PROVISION OF ARTICLE-5 (1-h) OF THE UNLICENSED ELECTRICITY GENERATION REGULATION IN THE ELECTRICITY MARKET (MW): 2377.11 MW

3-CAPACITIES FOR ELECTRIC POWER INCREASE REQUESTS TO BE MADE BY GENERATION LICENSE OWNERS WITH WIND OR SOLAR ENERGY PRIMARY: 175 MW

Source: Solarist